Maryland citizens slapped with $2 billion grid upgrade bill for out-of-state AI data centers — state complains to federal energy regulators, says additional cost breaks ‘ratepayer protection pledge’ promises

May 9, 2026

Electricity transmission towers
(Image credit: Shutterstock)

The Maryland Office of People’s Counsel (OPC), a state agency that represents its utility consumers, filed a complaint before the Federal Energy Regulatory Commission (FERC) regarding PJM Interconnection, LLC’s plans to charge it $2 billion of the $22 billion it spent to upgrade its grid to accommodate increasing demand from data centers. According to the OPC’s press release, this $2 billion bill will cost the state’s consumers an extra $1.6 billion in the next ten years alone — that means an extra $823 million for residential (approx. $345 per customer), $146 million for commercial (approx. $673 per customer), and $629 million for industrial customers (approx. $15,074 per customer).

“Without FERC action, Maryland customers face paying billions for transmission infrastructure that PJM is advancing to benefit data centers,” said Maryland People’s Counsel David S. Lapp. “PJM’s cost allocation rules are broken. Maryland customers have neither caused the need for these billions in new transmission projects nor will they meaningfully benefit from them.”

PJM Interconnection, LLC is the United States’ largest electricity transmission company, and covers 13 states plus Washington, D.C. This includes Delaware, Illinois, Indiana, Kentucky, Maryland, Michigan, New Jersey, North Carolina, Ohio, Pennsylvania, Tennessee, Virginia, and West Virginia, covering about 65 million people, or about 20% of the entire U.S. population. Some of these states, including Maryland, host a large number of data centers, so the firm needs to upgrade its infrastructure to meet projected demand from these power-hungry AI systems.

Latest Videos From

Maryland says that these infrastructure costs should be charged directly to the areas where they’re being constructed, or, as President Donald Trump made tech companies promise with the “ratepayer protection pledge,” the companies themselves should be billed directly for these grid upgrades. The OPC said there is “extreme uncertainty” regarding load growth driven by data center demand, and that utility providers tend to benefit from these upgrades even if the demand never materializes. This is especially true because the costs of these investments are borne by existing utility customers, not by the data centers themselves, if the data centers do not follow the “ratepayer protection pledge.”

Google Preferred Source

Follow Tom’s Hardware on Google News, or add us as a preferred source, to get our latest news, analysis, & reviews in your feeds.